How a six-week website project runs

/

The studio inside a converted warehouse: desks with monitors, a pinboard and a large-format printer

A website project with us takes six weeks, from kickoff to a site the client can edit on their own. Most clients ask what happens in those weeks before they sign, so here is the plan we send them, with the parts that tend to move.

Week one: questions and a site map

We start with a 90-minute call and a shared folder. By the end of the week the client has a one-page brief and a site map they have approved, and we have every login we need.

  • A brief in the client’s own words, read back to them
  • A site map with one line on the job of each page
  • A list of the photos, logos and documents we still need

Week two: words first

Claire writes the copy for every page before Marcus draws a single layout. Real words decide how long a heading runs and how much room a service needs, and they make the client’s review faster because there is something to read.

Weeks three to five: design and build

Design and build run together. We show the home page in the browser during week three, and the client reviews the rest on a phone and a laptop by the end of week five.

Three printed page layouts marked up on a desk
Page layouts, printed and marked up in the week-three review.

What we check before a review

  1. Every page at phone width
  2. Every form, sent to a real inbox
  3. Headings in order, and alt text on every image
  4. Page weight under 1 MB on the home page

We had a site we could edit ourselves six weeks after kickoff, and the booking form has not needed a change since.

Owen Parker, Clinic Director, Kestrel Physical Therapy

Week six: launch

Launch week is mostly checks. The step clients forget is the old site: links in emails, on business cards and in search results still point at its pages. We keep a redirect map from the first call and add it to the server the day before launch.

# Old addresses to new pages, added the day before launch
Redirect 301 /services.html /what-we-do/
Redirect 301 /about-us.html /about/
Redirect 301 /contact.php /contact/
Redirect 301 /book-online /book/

After launch we hold a 30-minute handover call and send a short guide to editing the site. Thanks for reading. If you have questions about how a project runs, ask in the comments.


Claire Bennett Avatar

3 responses to “How a six-week website project runs”

  1. Marcus Holloway Avatar
    Marcus Holloway

    The redirect map saves us every time. Starting it on the first call means nothing gets missed in launch week.

    1. Claire Bennett Avatar
      Claire BennettAuthor

      Agreed. It is the one document nobody asks for and everyone needs on launch day.

  2. Hannah Wright Avatar
    Hannah Wright

    The copy deadline in week two is the one most likely to move. We now book a working session with the client for it instead of waiting on a document.